M25 closure: Traffic disruption nowhere near as bad as everyone feared
They even finished work eight hours early
The first daytime total closure of the M25 motorway took place this weekend — and seemingly went off without a hitch, with the predicted traffic chaos failing to materialise.
A five-mile stretch of the motorway was closed from 9pm on Friday night (March 15) as work to widen the A3/ M25 interchange at J10 began.
It necessitated closing all lanes between J10 and J11, the A320 Chertsey Interchange, and diverting traffic around 12 miles on roads near Addlestone, Woking, Sheerwater, West Byfleet and Cobham.
With up to 6,000 vehicles typically using that stretch of the M25 every hour at weekends like the one just gone, the fear was that the diversion route would not be able to cope with the sheer volume of traffic.
Where have all the cars gone?
National Highways issued a warning for people to steer clear of the area and it seemed to have worked a treat — traffic flow was down by more than 50 per cent on normal levels as drivers heeded the advice.
And while there were reports of up to two miles of tailbacks on the M25 and A3 approaching both J10 and J11 at times, the predicted catastrophic meltdown of the local-roads infrastructure never arrived.
Indeed, as the author of Very British Problems, Rob Temple, found out for The Sunday Times when he ploughed into the area regardless of the warnings, it appeared as if the traffic drama had been significantly overplayed.
“It’s as we drive along the A320 through Ottershaw that we first see what lies ahead, what we truly face, which is: a completely clear road. Surely there’s been a mistake?
“Onwards we go, following the yellow signs, into West Byfleet and all the way through to the end of the diversion at the Junction 10 Wisley interchange. The whole diversion takes, ooh, 20 minutes. Not quite the five hours it’s supposed to.
“To check I’m not hallucinating, I go back and forth along the diversion multiple times throughout the day. Where the devil is everyone?”
Finished eight hours early
Better still, National Highways even finished this stage of the work early. The road was due to reopen at 6am today [Monday, March 18], but in fact the M25 reopened around 10pm last night, eight hours ahead of schedule.
Jonathan Wade, the National Highways project lead and the man who had told drivers to stay away from the south-western quadrant of the M25 while this weekend closure was in place, was understandably pleased at the outcomes of the project.
“We are delighted that we have been able to complete the work early and reopen the M25 ahead of schedule,” he said.
“Drivers have taken on board our advice, which reduced traffic levels by more than 50 per cent and meant the length of time added to journeys was around 30 minutes.
“Thank you to everyone for their cooperation that has made carrying out work on this major project to make journeys safer and reduce pollution much easier.
“We are extremely grateful to our delivery partners, Surrey County Council, the emergency services, and everyone else who has supported us this weekend.”
More closures coming
A further four total closures of the M25 will take place during the remainder of this year, with the next one scheduled for April.
The entire scheme will see the interchange at J10 enhanced to make the road safer and to allow for better traffic flow between the M25 and A3.
This first stage saw a footbridge demolished and the installation of a “very large gantry”. A heathland bridge will also be installed as part of the work, allowing wildlife to transit from Ockham Common to Wisley Common safely above the M25.
National Highways hopes the scheme will be completed and opened in summer 2025.
Related articles
- If you were interested in what happened when the M25 was shut, you may want to read how the public wants 60mph motorway speed limits – according to a WWF survey
- And check out how motorists are being fined millions of pounds for inadvertently entering low-traffic neighbourhoods
- Did you hear about the ‘boring’ M40 calendar that has been a roaring success?
Latest articles
- testing schedule 2
- test schedule
- F1 driver Lando Norris commissions bespoke open-top Land Rover Defender
- Citroën C3 and e-C3 2024 review: Petrol or electric, bow down before the new king of value cars
- Best-selling cars 2024: The UK’s most popular models
- Fourth-generation BMW 1 Series shows its new face with all-petrol line-up for the UK
- Cupra Tavascan 2024 review: Funky electric SUV continues Spanish brand’s EV roll
- Divine intervention? Trump-supporters’ motorhome destroyed after rolling into telegraph pole
- Extended test: 2023 Vauxhall Astra Sports Tourer GS PHEV